The construction of the metro in the river blocked the Main control Gastrula in the Dnipropetrovsk region.

It is stated in the letter from the head of the national Council of reforms under President Mikheil Saakashvili, writes gorsovet.com.ua passes mediaUA.
The document States: regional management Gastrula already for years (!) does not register a Notification of intent to start blasting at the construction sites of the Dnieper metro. Although, according to the Rules of safety during the handling of explosive materials promnaznacheniya must do so within 10 days.
Read also " mediaUA": "Party of mayors" - the idea of the Office of the President, it is not viable - Filatov
In the large-scale state project on completion of the metro in the river, which is financed by funds of international financial organizations was in jeopardy. The state suffers huge losses due to downtime Contracting construction company, suffers from the image of Ukraine in the eyes of foreign partners. In addition, the letter says head of the national Council reforms, the unfinished underground metro facilities pose a serious threat to buildings and residents in the Central part of the Dnieper.
We will remind, earlier the mayor of the Dnieper Boris Filatov has repeatedly stressed that the destructive position of officials Gastrula rips the implementation of major city infrastructure project.